The work on the King family house has begun! And oh what a difference two weeks can make! The workers and volunteers have already made huge progress:
1- The roof is completed
2- The transition between the existing home and the addition has been completed with new flooring, a new ceiling and has been insulated and is ready for drywall!
3- The new stairs have been installed up to the loft area
4- The furnace and heat pump are installed
5- The electric is all roughed in and ready for insulation!

The Towne Crier is writing a story on the Kings, keeping up with the weekly progress! It made front page of the Eastern Edition!! If you’d like to view this article, please read it online here: http://www.fairfieldtownecrier.com/EE-5-10-13.pdf

If you’d like to donate to the King family build, please visit our website at www.habitatfairfield.org and click on “DONATE” on the top left hand side of the page!

Thank you and God Bless,
From everyone at Habitat Fairfield and the King family

WEEK 1

WEEK 2